Phase I and Phase II ESAs have similar names, but they do different jobs. One looks for signs of a problem. The other tests for it. This guide explains the difference so you can order the right work at the right time.
The short version
A Phase I ESA asks, “Is there a reason to suspect contamination?” A Phase II ESA asks, “Is it there, and how much?” The Phase I uses records, a site visit, and interviews. The Phase II uses drilling, sampling, and lab tests.
Side-by-side comparison
| Phase I ESA | Phase II ESA | |
|---|---|---|
| Main question | Are there signs of contamination? | Is contamination present, and where? |
| Standard | ASTM E1527-21 | ASTM E1903 |
| Main methods | Records review, site visit, interviews, lien search | Soil, groundwater, or soil vapor sampling and lab tests |
| Field work | Visual walk of the site | Drilling, borings, or wells |
| Supports buyer defense | Yes, when it meets all appropriate inquiry | Not by itself |
| Typical trigger | Purchase, refinance, or new loan | A concern found in the Phase I |
| Typical time | Two to three weeks | Three to six weeks, based on lab and access |
What a Phase I ESA does
A Phase I is a desk study plus a site visit. The environmental professional reviews historical maps, aerial photos, agency records, and past reports. The team walks the property and nearby areas. They interview owners and occupants. A search for environmental cleanup liens is also part of the process.
Why lenders and buyers ask for it
In Washington, the Model Toxics Control Act (MTCA) makes liability strict, joint, and several. A buyer may be liable for contamination that a past owner caused. A buyer defense needs “all appropriate inquiry” before the purchase. EPA recognizes ASTM E1527-21 as a way to meet that rule.
The result of a Phase I is a list of findings. The most important are recognized environmental conditions (RECs). Under ASTM E1527-21, a REC means hazardous substances or petroleum products are present because of a release, are likely present because of a release, or pose a material threat of a future release.
For time limits on a Phase I, see how long a Phase I ESA is valid.
What a Phase II ESA does
A Phase II tests the concerns from the Phase I. ASTM E1903 describes it as a process based on the scientific method. The goal is sound, valid data on actual property conditions.
How a Phase II is scoped
The consultant starts with your goals and the Phase I findings. Then the consultant picks where to sample and what to test. A former dry cleaner may need soil vapor and groundwater samples. A former gas station may need soil and groundwater samples near the tanks and dispensers. A former auto shop may need tests for petroleum and metals.
ASTM E1903 also says that a Phase I label is not final. A condition that the Phase I called a REC, or did not, does not decide the Phase II scope by itself. The Phase II team uses its own judgment.
Common Phase II methods
| Method | What it tests | Typical use |
|---|---|---|
| Soil borings | Soil at set depths | Tanks, spills, fill, past industry |
| Temporary or permanent wells | Groundwater | Solvents, fuel, deeper releases |
| Soil vapor probes | Gas in soil pores | Dry cleaners, solvent use, vapor risk to buildings |
| Surface samples | Shallow soil or sediment | Stained areas, storage yards |
| Building materials | Asbestos, lead paint | Renovation or demolition plans |
When one round is not enough
ASTM E1903 notes that a single round of sampling may not give enough data. If the first results are unclear, the team may need more samples. Plan time and budget for that chance.
Which one do you need?
Most deals start with a Phase I. A Phase II is a choice that you make after you read the Phase I.
You likely need only a Phase I if
- The Phase I finds no RECs.
- Your lender accepts the Phase I as is.
- Your attorney agrees that no more testing is needed.
You likely need a Phase II if
- The Phase I lists one or more RECs.
- The site had a gas station, dry cleaner, auto shop, or industrial use.
- Your lender asks for testing as a loan condition.
- You plan to dig, build, or change the use of the site.
The Phase II checker can help you sort your Phase I findings. For a deeper guide, read what to do when a Phase I finds a REC.
Cost and timing differences
A Phase I usually costs less and moves faster than a Phase II. The Phase I is mostly desk work and one site visit. The Phase II adds drilling crews, lab fees, and more field time.
Phase II cost depends on the number of samples, the depth, and the lab tests. Drilling inside a building or under a paved lot also takes more effort. Lab turnaround can add days or weeks.
| Factor | Phase I | Phase II |
|---|---|---|
| Field crew | Environmental professional | Professional plus drilling crew |
| Lab costs | None | Yes, per sample and test |
| Main schedule risk | Agency records requests | Drilling access and lab times |
Plan your due diligence period with both in mind. If a Phase II is likely, ask for more time in your purchase agreement. For Phase I budget details, see Phase I ESA cost in Washington.
What happens after a Phase II
The lab results go into a report. The report compares the results to cleanup levels under Washington’s MTCA rules in WAC 173-340. If results are below those levels, the deal may move on. If they are above, you may need more work.
Many owners use Ecology’s Voluntary Cleanup Program to clean up a site and seek a No Further Action opinion. Read our guide on the VCP and No Further Action in Washington.